Implementation of lean production
nuclear industry
  • Problem point
    Implementation of lean production
  • Resources
    рабочая группа из 6 празделинии (производство, бесплатный оборудование, технологическое, производство, шкад, ПЕО).
  • Key stages
    - conducting trainings on the basics of the lean production system – 2 weeks;
    - audit of production processes and identification of bottlenecks – 1 week;
    - team formation and product selection for key BP events – 1 week;
    - calculation and fixation of the time of the flow of processes (ВПП) according to the selected product – 0.5 weeks;
    - development of a plan of measures for BP implementation – 1 week;
    - development of a training plan for command elements of BP – 0.5 weeks;
    - support for implementation of BP elements in production – 6 weeks;
  • Results
    - время протекания процессов (ВПП) is reduced by 20%;
    - the volume of unfinished production is reduced by 15%.