Lean production integration
nuclear industry
  • Core pain
    Processes were dragging out too long and unfinished inventory was piling up between stations, clogging the floor and locking up working capital.
  • Final results
    We cut total production cycle times by a clean 20% and reduced the volume of unfinished, bottlenecked inventory by 15%.
  • Key stages
    Twelve weeks total: two weeks training, two weeks mapping bottlenecks, two weeks planning process changes, and six weeks on-the-floor implementation.
  • Resources used
    We ran this with a six-department floor team: production, maintenance, engineering, logistics, warehouse, and the economic planning department.