Calculation of loading equipment
nuclear industry
  • Problem point
    calculation of loading equipment
  • Resources
    working group of 4 divisions (sales, planning, technological, production).
  • Key stages
    - familiarization with the equipment park and categorization (basic, auxiliary) – 0.5 weeks;
    - изучение технологии производитель – 1 week;
    - digitization of production cycles and norms of operations - 2 weeks;
    - synchronization of sales plan and production plan – 1 week;
    - construction of algorithms for calculation of loading of production (sites, equipment) – 2 weeks;
    - construction of production reporting and analytics in sections: data, sections, equipment, work. staff – 1 week.
  • Results
    - the calculation of the loading of the equipment takes less time;
    - the possibility of calculating the loading of the equipment under different scenarios is created;
    - on the basis of innovations, it became possible to forecast loading in future periods.