Key stages
- familiarization with the equipment park and categorization (basic, auxiliary) – 0.5 weeks;
- изучение технологии производитель – 1 week;
- digitization of production cycles and norms of operations - 2 weeks;
- synchronization of sales plan and production plan – 1 week;
- construction of algorithms for calculation of loading of production (sites, equipment) – 2 weeks;