Supply and site coordination
nuclear industry
  • Core pain
    Delivery trucks and installation crews were completely out of sync, leaving expensive equipment sitting in storage while builders stood around idle.
  • Final results
    We cut crew downtime by 15–20%, stopped wasting money on extra warehouse space, and made our forecasting models 20% more accurate.
  • Key stages
    Four weeks total: one week tracking where the scheduling delays happened, two weeks syncing files, and one week launching daily reports.
  • Resources used
    We ran this using an independent operational team built from four floor departments: the planners, logistics drivers, warehousemen, and site builders.