Synchronization of the equipment supply schedule
with construction work
nuclear industry
  • Problem point
    Synchronization of the equipment supply schedule with construction work.
  • Resources
    independent team from 4 subdivisions (planning, logistics, storage, construction)
  • Key stages
    - analysis of the current situation and identification of growth points - 1 week;
    - synchronization of working files and creation of a single information field – 2 weeks;
    - setting up the system of regular reporting and analytics for decision-making – 1 week.
  • Results
    - reduction of storage costs, reduced downtime of the brigade by 15-20%.
    - increasing the speed and accuracy of forecasting by 20%.